1.  HEADS OF FIELD ELEMENTS.

    a.   Establish internal procedures to assure compliance with provisions
         of this Order and other regulations or instructions issued by
         SA-20.

    b.   Designate, when needed and with the approval of SA-20, persons to
         serve as DOE Classification Officers.  Review contractor
         nominations for Classification Officers and recommend SA-20
         approval.

    c.   Request of SA-20, as needed for Field Elements or contractors, if
         appropriate, under their jurisdiction, designations of
         classification authority for and maintain a listing of:

         (1)  Original Classification Authority (all levels -- Government
              only);

         (2)  Top Secret Derivative Classification Authority; and

         (3)  Derivative Declassification Authority.

    d.   Assure designation of Secret and Confidential Derivative
         Classifiers, as necessary, and ensure that a listing is maintained
         of such classifiers for Field Elements or contractors under their
         jurisdiction.

    e.   Assure participation by appropriate Classification Officers and
         other personnel with classification responsibility in the early
         planning stages of new programs that have potential for involving
         or generating classified information.

    f.   Before commencement of Category II or Category III non-DOE-funded
         work, conduct a review of the work request and certify that the
         sponsoring organization has either provided the appropriate
         classification guidance or has stated in writing that the
         non-DOE-funded work will not entail classified activities.

    g.   Obtain classification guidance from SA-20 for programs under their
         purview that concern potentially classified subject areas.

    h.   Assist SA-20 in preparing and revising program classification
         guides.

    i.   Assure that Field Elements and contractors under their jurisdiction
         prepare local classification guides or receive program
         classification guides approved for this purpose covering all
         classified work being performed.

         (1)  Where delegated such authority, approve local classification
              guides for implementation, providing final copies for the
              record to SA-20 (see page V-10, Chapter V, Part B, paragraph
              6).

         (2)  Where local approval authority has not been delegated, submit
              proposed local classification guides and substantive changes
              in local classification guides to SA-20 for approval prior to
              their issuance.

    j.   Assure that approved classification guidance is included with
         authorization of new work initiated by Field Elements or
         contractors under their jurisdiction when such work is likely to
         concern classified subject area and provide copies of such guidance
         to SA-20 at the time of initial distribution.

    k.   Where delegated such authority by SA-20, assure that the denial
         authority described on page II-3, Chapter II, Part A, paragraph
         4a(8)(a), is applied according to the provision of all applicable
         DOE Orders and any specific instructions in the delegation.

    l.   Assure that DOE and DOE contractor personnel within their
         jurisdiction who publish or deliver papers at conferences or any
         other presentation concerning potentially classified subject areas
         are informed on existing classification guidance in the subject
         areas of their papers and advised as to potential danger areas in
         the discussion following their presentations.

    m.   Assure that all documents and material prepared within their
         jurisdiction by DOE or DOE contractor personnel concerning
         potentially classified subject areas receive appropriate
         classification review.

    n.   Provide SA-20 with information required to be maintained by SA-20
         or reported to the ISOO in accordance with Executive Order 12356
         and its implementing directives, or as determined to be required by
         SA-20.

    o.   Establish, when necessary, detailed procedures for special
         large-scale reviews of accumulations of classified documents in
         their Field Elements.  All such plans developed by Field Elements
         or contractors under their jurisdiction shall be forwarded to SA-20
         for approval.

    p.   Develop and conduct a classification appraisal program for their
         Field Elements and contractors involved with classified
         information; be cognizant of the DOE Classification Appraisal
         Procedural Guide; follow up on appraisal findings requiring
         corrective action; take action on recommendations made in
         appraisals of the classification programs under their supervision;
         ensure that contractor organizations conduct classification
         appraisals of their entities involved with classified information.

    q.   Take appropriate and prompt corrective action whenever a
         classification violation occurs within their Field Elements.

    r.   Assure that an appropriate classification education program is
         conducted for DOE and DOE contractor organizations under their
         jurisdiction.

    s.   Appoint Classification Boards, as appropriate.

    t.   Assure that Heads of contractor organizations discharge, in
         relation to their own organization, subcontractors, and suppliers,
         the responsibilities and authorities specified in subparagraphs a
         through q, above, by including appropriate provisions in their
         contracts.  If these responsibilities entail submission of
         information to SA-20, it should be made through the appropriate
         Departmental element.

    u.   Designate an individual(s) to be responsible for bringing to the
         attention of the contracting officer each procurement falling
         within the scope of this Order.  Unless another individual is
         designated, the responsibility is that of the procurement request
         originator (the individual responsible for initiating a requirement
         on DOE F 4200.33, "Procurement Request-Authorization").

2.  FIELD ELEMENT AND CONTRACTOR CLASSIFICATION OFFICERS.

    a.   Assist or act for the Head of their Field Element or contractor
         organization, as appropriate, in exercising their responsibilities
         and authorities for classification and declassification programs.

    b.   Maintain continuous contact with appropriate technical staff
         personnel and with other Classification Officers in related
         programs.

    c.   Provide classification guidance to employees within their
         organization and, as appropriate, to their contractors or
         subcontractors.

    d.   Coordinate the preparation of local classification guides for
         fields of operation or programs within their purview.

    e.   Assure that DOE and DOE contractor personnel within their
         jurisdiction who publish or deliver papers at conferences or any
         other presentation concerning potentially classified subject areas
         are informed on existing classification guidance in the subject
         areas of their papers and advised as to potential danger areas in
         the discussion following their presentation.

    f.   Assure that all documents and material prepared by DOE or DOE
         contractor personnel within their jurisdiction concerning
         potentially classified subject areas receive appropriate
         classification review.

    g.   Provide technical advice, as requested, to SA-20.

    h.   Initiate classification and declassification reviews of documents
         originated within their organizations.

    i.   Supervise special declassification activities or reviews.

    j.   Conduct classification appraisals of their contractor or
         subcontractor organizations.

    k.   Conduct classification education programs for their organizations
         and assure that such programs are conducted by their contractors
         and subcontractors.

    i.   Appoint Classification Boards, as appropriate.

    m.   Ensure that appropriate classification guidance or a written
         statement that no classified information will be involved is
         provided to the cognizant DOE Field Element prior to the
         commencement of Category II or Category III non-DOE-funded work in
         accordance with procedures established by the Field Element
         Classification Officer.

    n.   Appoint Responsible Reviewers, as appropriate.

3.  RESPONSIBLE REVIEWERS.

    a.   Advise Field Element and contractor Classification Officers and
         SA-20 with regard to the technical aspects of information within
         their fields of expertise.

    b.   Make recommendations to Field Element and contractor Classification
         Officers and SA-20 regarding the declassification or continued
         classification of documents or material submitted for their review.

4.  FIELD ELEMENT AND CONTRACTOR EMPLOYEES.

    a.   Refer questions concerning classification or declassification of
         (1) information or (2) documents or material to Authorized
         Classifiers, their classification office, or through channels to
         SA-20.

    b.   Obtain a determination from an Authorized Classifier on (1)
         information or (2) documents or material whose classification is in
         question.

    c.   Refer suggestions, complaints, or challenges concerning the DOE
         classification and declassification program to their classification
         office or through channels to SA-20.